The Aerotropolis 132kV Feeder Stage 3B serves as a critical infrastructure project to fuel the Western Sydney's long-term expansion and energy needs. 


The project scope consisted of: 


  • 1.2km of new conduit installations, installation of joint bays, cat holes, earthing / FO pits and associated works. 

  • Horizontal directional under bores under Cosgrove Creek and South Creek which required specific Frac-Out management plans and a mitigation methodology to prevent Frac-Out. 

  • Construction of robust 132kV joint bays. Creation of access tracks for heavy vehicles and crane operations. 

  • Use of specialised equipment and innovative methodologies.