top of page

Penrith Stadium Sewer Relocation Works

SECTORS:

WATER & WASTEWATER

CLIENT:

Infrastructure NSW

REGION:

NSW

STATUS

Complete

COMPLETION DATE:

Infrastructure NSW is delivering the Penrith Stadium Project on behalf of the Office of Sport. As part of the upgrade, ground capacity will be increased to approximately 25,000. Vaughan Infrastructure was engaged by Infrastructure NSW to conduct the realignment of two Sydney Water rising mains and a Sydney Water gravity sewer as part of the major project.


Scope of Works


Realignment of Sewer Mains

  • RM1 & RM2 DN500 DICL Pipes

  • Potholing & Investigation Works

  • Auger & Pour Thrust Block Piles

  • Strip Topsoil & Prep Ground

  • Construct RM1 RM2 Dual Trench & lay Gravity Mains CH002-CH114

  • Construct thrust blocks to RM1 & RM2 DN500 mains

  • Struct RM1 RM2 Dual Trench & lay Gravity Mains CH114.7-CH212.9

  • Commissioning & Testing to RM1 & RM2 DN500 mains

  • Cutover of new mains

  • Grout fill existing disused mains

Gravity Sewer Main Realignment

  • Strip Topsoil & Pavement & Extend Site Boundary

  • Excavate & install DN150 pipework

  • Construct DN1200 Manhole Chambers

  • Commissioning & Testing

  • Connection to existing manhole

  • Grout fill existing disused mains

  • Reinstatement to south carpark


Challenges


Site access constraints

With multiple contractors working on site, Vaughan navigated varied site access constraints through effective coordination and clear communication with stakeholders, fostering positive relationships and ensuring the project remained on schedule.


Undisturbed public operations

The Penrith Cricket Club grounds consists of three ovals and is located adjecent to the Penrith Stadium, it was critical that the ground and public space remained operational throughout construction. Vaughan ensured that all works were completed safely with appropriate cordoning measures.


Archaeological Requirements 


Heritage NSW requested that archaeological trial holes be dug prior to construction to ensure that it was not an area of archaeological significance. An investigation was undertaken in collaboration with our licenced asbestos assessor and specialist heritage consultant, to ensure the area did not present any contamination or heritage significance. Seven test holes were investigated with no notable findings.

bottom of page