Sydney Program Alliance Arthur Street

SECTORS:

POWER & ENERGY

CLIENT:

Sydney Program Alliance

REGION:

NSW

STATUS

Complete

COMPLETION DATE:

As part of the primary scope for the Warringah Freeway Upgrade project, SPA awarded Vaughan Infrastructure the contract to complete all ASP Level 1 & 2 works for the various Ausgrid Asset Relocations required to allow for the RMS road alignment and widening works. 


Scope of works include: 


  • Coordinating all works with Ausgrid representatives 

  • 600mTrenching, conduit install and backfill for all proposed underground electrical network to Ausgrid Standards 

  • Supply and install of new poles, including supply and install of new overhead electrical cabling and UGOHs as required by the approved Ausgrid drawings 

  • Supply and install of 1 LV Pillar 

  • 3800m of cable installation 

  • Coordinating and undertaking works necessary to complete outages and cutovers 

  • Carrying out all ASP Level 1 & 2 works 

  • Removal of all redundant temporary assets (Cables and conduit)