As part of the primary scope for the Warringah Freeway Upgrade project, SPA awarded Vaughan Infrastructure the contract to complete all ASP Level 1 & 2 works for the various Ausgrid Asset Relocations required to allow for the RMS road alignment and widening works.
Scope of works include:
Coordinating all works with Ausgrid representatives
600mTrenching, conduit install and backfill for all proposed underground electrical network to Ausgrid Standards
Supply and install of new poles, including supply and install of new overhead electrical cabling and UGOHs as required by the approved Ausgrid drawings
Supply and install of 1 LV Pillar
3800m of cable installation
Coordinating and undertaking works necessary to complete outages and cutovers
Carrying out all ASP Level 1 & 2 works