Wilton Southeast Pipeline Protection Program
SECTORS:
GAS & FUEL
CLIENT:
APA Group
REGION:
NSW
STATUS
Complete
COMPLETION DATE:
Awarded the contract as the Principal Contractor for the Pipeline Protection Works project in Wilton.
Scope of works include:
Installation of 1468m of concrete slabbing for the Moomba Sydney Ethane Pipeline (Ethane DN200)
Installation of 735m of concrete protection slabbing for the Moomba Wilton Pipeline (MSP Natural Gas DN850)
Integrity check and recoating of the Moomba Wilton Pipeline (MSP Natural Gas DN850) under 3 new road crossings and 2 other known defect locations – 82.5m worth (Coating (Coal Tar Enamel) removal
Visual Inspection
100% MPI of the entire pipe exposed surface
Abrasive Blasting
Recoating
Transition/coating interface with existing
Final Coating Inspection